Industrial Projects > Electricity Generation - Coal Based > Bellary Thermal Power Project Phase I
Bellary Thermal Power Project Phase I
Company: Karnataka Power Corpn. Ltd.
Ownership: State Govt. - Commercial Enterprises
Project Location: Kuditini, Dist. Bellary, Karnataka, India
Contact: B N Viswanath / Chief Engineer Secondary Contact: Mr. Bendre / Supdt. Engineer
Project Status: Active Project Type/Scale: New Unit
Industry: Electricity Generation - Coal Based
Investment/Estimated Cost: Rs. 2,100.00 Crores / USD 525.00 Million
More projects (By Karnataka Power Corpn. Ltd.):
Ownership: State Govt. - Commercial Enterprises
Project Location: Kuditini, Dist. Bellary, Karnataka, India
Contact: B N Viswanath / Chief Engineer Secondary Contact: Mr. Bendre / Supdt. Engineer
Project Status: Active Project Type/Scale: New Unit
Industry: Electricity Generation - Coal Based
Investment/Estimated Cost: Rs. 2,100.00 Crores / USD 525.00 Million
Tuesday, March 16, 1999 | Invited co-promoters |
---|---|
Wednesday, June 30, 1999 | Initial commissioning date |
Saturday, March 2, 2002 | Foundation stone laid |
Friday, June 28, 2002 | CEA (Central Electricity Authority) approval received |
Saturday, June 14, 2003 | Project bids awarded |
Friday, July 18, 2003 | Project bids awarded |
Thursday, May 6, 2004 | Financial closure achieved |
Saturday, December 31, 2005 | Revised commissioning date |
Wednesday, April 30, 2008 | Commercial production expected |