Find Projects:

Captive Power Project

Company: Madras Aluminium Co. Ltd.
Ownership: KCP Group
Project Location: India

Project Status: Completed  Project Type/Scale: New Unit
Industry: Electricity Generation - Diesel Based
Investment/Estimated Cost: Rs. 225.00 Crores / USD 56.25 Million
Monday, July 1, 1996Date of announcement
Wednesday, March 31, 1999Revised commissioning date
Wednesday, March 31, 1999Initial commissioning date
Friday, April 30, 1999Trial run commenced
Sunday, October 31, 1999Completed