Industrial Projects > Shipping > Coal Handling Jetty Project
Coal Handling Jetty Project
Company: Paradip Port Trust
Ownership: Central Govt. - Commercial Enterprises
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Shipping
Investment/Estimated Cost: Rs. 831.11 Crores / USD 207.78 Million
More projects (By Paradip Port Trust):
Ownership: Central Govt. - Commercial Enterprises
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Shipping
Investment/Estimated Cost: Rs. 831.11 Crores / USD 207.78 Million
Friday, April 30, 1993 | Central Government approval received |
---|---|
Sunday, June 30, 1996 | Expenses incurred till 1 (Rs. 41.47 Crores) |
Monday, March 31, 1997 | Budgetary allocation (Rs. 41.47 Crores) |
Thursday, April 30, 1998 | Revised commissioning date |
Wednesday, September 30, 1998 | Initial commissioning date |
Sunday, April 30, 2000 | Revised commissioning date |
Saturday, March 31, 2001 | Trial run commenced |
Saturday, March 31, 2001 | Revised commissioning date |
Tuesday, September 11, 2001 | Completed |
Sunday, September 30, 2001 | Completion by |
More projects (By Paradip Port Trust):