 Industrial Projects > Electricity Distribution > East-North Tala Transmission System Project

East-North Tala Transmission System Project

Company: Powerlinks Transmission Ltd.
Ownership: Tata Group
Project Location: India
Contact: Firdose Vandrevala / Director

Project Status: Completed  Project Type/Scale: New Unit
Industry: Electricity Distribution
Investment/Estimated Cost: Rs. 2,800.00 Crores / USD 700.00 Million
Friday, November 2, 2001CEA (Central Electricity Authority) approval received
Friday, January 24, 2003PIB (Public Investment Board) approval received
Friday, May 23, 2003Project bids awarded
Saturday, June 28, 2003CCEA (Cabinet Committee on Economic Affairs) approval received
Wednesday, December 24, 2003Foundation stone laid
Monday, January 5, 2004Project bids awarded
Friday, January 9, 2004Financial closure achieved
Friday, January 30, 2004Project bids awarded
Monday, June 7, 2004Project bids awarded
Monday, April 10, 2006Partially commissioned
Monday, July 31, 2006Initial commissioning date
Wednesday, June 20, 2007Completed