Industrial Projects > Electricity Generation - Hydel Based > Kalindi Hydel Power Project Stage Ii
Kalindi Hydel Power Project Stage Ii
Company: Karnataka Electricity Board
Ownership: State Electricity Boards
Project Location: India
Project Status: Stalled Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 445.22 Crores / USD 111.31 Million
More projects (By Karnataka Electricity Board):
Ownership: State Electricity Boards
Project Location: India
Project Status: Stalled Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 445.22 Crores / USD 111.31 Million
Wednesday, May 14, 1980 | Planning Commission approval received |
---|---|
Thursday, March 31, 1988 | Initial commissioning date |
Monday, March 31, 1997 | Revised commissioning date |
Wednesday, May 14, 1997 | Stalled |
Tuesday, March 31, 1998 | Revised commissioning date |