Find Projects:

Karbi Langpi Hydel Project

Company: Assam State Electricity Board
Ownership: State Electricity Boards
Project Location: Lower Borpani river, Hatidubi, Amtereng, Assam, India
Contact: P Handique / Chief Engineer

Project Status: Completed  Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 360.00 Crores / USD 90.00 Million
Monday, September 24, 1979Planning Commission approval received
Saturday, March 6, 1993MoU signed
Friday, March 31, 1995Initial commissioning date
Wednesday, December 31, 2003Revised commissioning date
Friday, March 31, 2006Revised commissioning date
Friday, February 2, 2007Completed
Wednesday, February 28, 2007Revised commissioning date

More projects (By Assam State Electricity Board):
• 132D/C Garmur-Nazira Transmission Line• 132Kv S/C Garmur-Bokakhad Trans. Line• 132S/C Rangia-Sipajhar-Rowta-Depota Line
• Amguri Power• Bongaigaon Thermal Power• Bongaigaon Transmission
• Dalaima Power• Guwahati Transmission• Karbi Langpi Hydel
• Lakwa Waste Heat Recovery• Nagaon Transmission• Nalbari District Rural Electrification
• Rangia Transmission• Sibsagar Transmission• Tezpur Transmission
• Udaipur Power Project (Borgolai)• Dhansiri Hydel Power• Lakwa Waste Heat
Videos   |   Useful Links   |   FREE Magazines
HomeBuyAdd FREE ListingAdvertise Industrial CompanyIndustrial Portal