Industrial Projects > Coal & Lignite > Koyagudem O C P Mine Project
Koyagudem O C P Mine Project
Company: Singareni Collieries Co. Ltd.
Ownership: Central Government
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Coal & Lignite
Investment/Estimated Cost: Rs. 25.84 Crores / USD 6.46 Million
More projects (By Singareni Collieries Co. Ltd.):
Ownership: Central Government
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Coal & Lignite
Investment/Estimated Cost: Rs. 25.84 Crores / USD 6.46 Million
Sunday, September 30, 2001 | Cabinet approval received (Rs. 25.84 Crores) |
---|---|
Monday, March 31, 2003 | Expenses incurred till 1 (Rs. 6.12 Crores) |
Wednesday, March 31, 2004 | Initial commissioning date |
Friday, April 30, 2004 | Completed |
Monday, August 2, 2004 | Date of announcement |
More projects (By Singareni Collieries Co. Ltd.):