Industrial Projects > Electricity Generation - Hydel Based > Larji Hydel Power Project
Larji Hydel Power Project
Company: Himachal Pradesh State Electricity Board
Ownership: State Electricity Boards
Project Location: Jawahar Nagar, Distt: Mandi, HP, India
Phone: 01905-35054 / 37163/ 37367 Fax: 35054
Contact: Er P K Verma / Dy. Chief Engineer Secondary Contact: R K Juneja / Chief Engineer
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 1,200.00 Crores / USD 300.00 Million
More projects (By Himachal Pradesh State Electricity Board):
Ownership: State Electricity Boards
Project Location: Jawahar Nagar, Distt: Mandi, HP, India
Phone: 01905-35054 / 37163/ 37367 Fax: 35054
Contact: Er P K Verma / Dy. Chief Engineer Secondary Contact: R K Juneja / Chief Engineer
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 1,200.00 Crores / USD 300.00 Million
Monday, March 30, 1987 | Planning Commission approval received |
---|---|
Tuesday, March 31, 1992 | Initial commissioning date |
Saturday, April 1, 1995 | Date of announcement |
Friday, April 30, 1999 | Revised commissioning date |
Wednesday, March 29, 2000 | CEA (Central Electricity Authority) approval received |
Tuesday, April 23, 2002 | Project bids awarded |
Wednesday, December 31, 2003 | Revised commissioning date |
Sunday, October 31, 2004 | Revised commissioning date |
Thursday, June 30, 2005 | Revised commissioning date |
Friday, March 31, 2006 | Revised commissioning date |
Sunday, December 31, 2006 | Completed |
Sunday, December 31, 2006 | Completion by |