Thursday, February 3, 1983Planning Commission approval received
Sunday, March 31, 1991Initial commissioning date
Monday, March 31, 1997Revised commissioning date
Monday, December 8, 1997Completed
Wednesday, December 31, 1997Completion by

More projects (By Kerala State Electricity Board):
• Athirappally Hydel Power• Brahmapuram Power• Cherthala Power Transmission
• Kakkad Hydel Power• Karapara-Kuriarkutty Hydel Power• Kuttiyadi Hydel Power
• Kuttiyadi Hydel Power Project I I• Malankara Hydel Power• Mankulam Hydroelectric
• Muvathupuzha Hydel Power• Nallalam Power• Neriamangalam Hydel Power
• Pallipuram-Pothangod Transmission• Pallivasal Extn Hydel Power• Pathrakadavu Hydro Power
• Pothangod-Kattakada Transmission• Rural Electrification• Thottiyar Hydel Power
• Thumba 110-Kv Substation• Baitarani Coal Mines Thermal Power Station• Cheemeni Coal Based Super Thermal Power
• Pambar Hydro Electric Power• Pooyamkutty Hydro Electric Power• Vakkallar Hydro Electric Power
Videos   |   Useful Links   |   FREE Magazines
HomeBuyAdd FREE ListingAdvertise Industrial CompanyIndustrial Portal