Industrial Projects > Shipping > M R P L Captive Jetty Project
M R P L Captive Jetty Project
Company: New Mangalore Port Trust
Ownership: Joint Sector
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Shipping
Investment/Estimated Cost: Rs. 125.00 Crores / USD 31.25 Million
More projects (By New Mangalore Port Trust):
Ownership: Joint Sector
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Shipping
Investment/Estimated Cost: Rs. 125.00 Crores / USD 31.25 Million
Monday, April 6, 1998 | Cabinet approval received |
---|---|
Wednesday, March 31, 1999 | PIB (Public Investment Board) approval received |
Sunday, July 4, 1999 | Date on which environmental clearance was received |
Wednesday, July 31, 2002 | Partially commissioned |
Monday, September 30, 2002 | Completed |
More projects (By New Mangalore Port Trust):
• | Cruise Terminal | • | General Cargo Berth (Deep Draft Multipurpose Berth) | • | Jetty & Dredging |
• | Lng Terminal | • | Railway Infrastructure Upgrading | • | Iron Ore Handling Facility Project At Berth 14 |