Industrial Projects > Storage & Distribution > Mangalore-Hassan Bangalore Pipeline Project
Mangalore-Hassan Bangalore Pipeline Project
Company: Petronet M H B Ltd.
Ownership: Joint Sector
Project Location: HPCL-POL Terminal, Village Bala,Via Katipalla, Mangalore, Dakshin Kannad, Karnataka, India
Contact: S.B. Pandey / MD
Project Status: Completed Project Type/Scale: New Unit
Industry: Storage & Distribution
Investment/Estimated Cost: Rs. 747.00 Crores / USD 186.75 Million
Ownership: Joint Sector
Project Location: HPCL-POL Terminal, Village Bala,Via Katipalla, Mangalore, Dakshin Kannad, Karnataka, India
Contact: S.B. Pandey / MD
Project Status: Completed Project Type/Scale: New Unit
Industry: Storage & Distribution
Investment/Estimated Cost: Rs. 747.00 Crores / USD 186.75 Million
Saturday, May 31, 1997 | Central Government approval received |
---|---|
Tuesday, March 10, 1998 | Project bids awarded |
Wednesday, July 1, 1998 | Date of announcement |
Sunday, March 31, 2002 | Initial commissioning date |
Monday, March 31, 2003 | Revised commissioning date |
Monday, June 30, 2003 | Trial run commenced |
Thursday, July 31, 2003 | Completion by |
Saturday, October 11, 2003 | Completed |