Industrial Projects > Synthetic yarn > P O Y Project
P O Y Project
Company: Rajashree Polyfil Ltd. [Merged]
Ownership: Birla B.K. Group
Project Location: Shir, Bharuch, Gujarat, India
Project Status: Completed Project Type/Scale: New Unit
Industry: Synthetic yarn
Investment/Estimated Cost: Rs. 556.38 Crores / USD 139.10 Million
Ownership: Birla B.K. Group
Project Location: Shir, Bharuch, Gujarat, India
Project Status: Completed Project Type/Scale: New Unit
Industry: Synthetic yarn
Investment/Estimated Cost: Rs. 556.38 Crores / USD 139.10 Million
Monday, July 4, 1994 | Public issue (Rs. 259.00 Crores) |
---|---|
Sunday, March 31, 1996 | Initial commissioning date |
Friday, May 31, 1996 | Revised commissioning date |
Sunday, June 30, 1996 | Expenses incurred till 1 (Rs. 471.00 Crores) |
Tuesday, December 31, 1996 | Trial run commenced |
Sunday, March 30, 1997 | Commercial production expected |
Saturday, May 31, 1997 | Completed |