Industrial Projects > Electricity Generation - Coal Based > Padubidri (Mangalore) Power Project
Padubidri (Mangalore) Power Project
Company: Nagarjuna Power Corpn. Ltd.
Ownership: Nagarjuna Group
Project Location: Nandikur, Distt. Dakshin Kannad, Karnataka, India
Phone: 0091-80- 3517308, 3517309 Fax: 0091-80- 3517169
Contact: K S Balachandra / GM - Technical Secondary Contact: K S Raju / Vice CH & MD
Project Status: Active Project Type/Scale: New Unit
Industry: Electricity Generation - Coal Based
Investment/Estimated Cost: Rs. 4,342.00 Crores / USD 1,085.50 Million
Ownership: Nagarjuna Group
Project Location: Nandikur, Distt. Dakshin Kannad, Karnataka, India
Phone: 0091-80- 3517308, 3517309 Fax: 0091-80- 3517169
Contact: K S Balachandra / GM - Technical Secondary Contact: K S Raju / Vice CH & MD
Project Status: Active Project Type/Scale: New Unit
Industry: Electricity Generation - Coal Based
Investment/Estimated Cost: Rs. 4,342.00 Crores / USD 1,085.50 Million
Tuesday, February 28, 1995 | MoU signed |
---|---|
Monday, April 1, 1996 | Date of announcement |
Friday, June 14, 1996 | CEA (Central Electricity Authority) approval received |
Saturday, January 25, 1997 | Project bids awarded |
Monday, January 25, 1999 | Date on which environmental clearance was received |
Thursday, April 29, 1999 | CEA (Central Electricity Authority) approval received |
Wednesday, August 4, 1999 | PPA (Power purchase agreement) signed |
Monday, May 1, 2000 | Expenses incurred till 1 (Rs. 50.00 Crores) |
Sunday, March 31, 2002 | Expenses incurred till 1 (Rs. 60.00 Crores) |
Sunday, March 31, 2002 | Initial commissioning date |
Monday, June 23, 2003 | Project bids awarded |
Wednesday, June 30, 2004 | State government approval received |
Tuesday, November 30, 2004 | Cabinet approval received |
Friday, January 28, 2005 | PPA (Power purchase agreement) signed |
Wednesday, October 18, 2006 | Financial closure achieved |
Saturday, March 31, 2007 | Revised commissioning date |
Thursday, December 31, 2009 | Completion by |