Company: Gujarat Paguthan Energy Corpn. Pvt. Ltd.
Ownership: Torrent Group
Project Location: Paguthan,Distt. Bharuch, Gujarat, India

Project Status: Completed  Project Type/Scale: New Unit
Industry: Electricity Generation - Gas Based
Investment/Estimated Cost: Rs. 2,247.00 Crores / USD 561.75 Million
Thursday, November 25, 1993CEA (Central Electricity Authority) approval received
Wednesday, February 2, 1994PPA (Power purchase agreement) signed
Saturday, April 30, 1994Date on which environmental clearance was received
Tuesday, February 28, 1995Financial closure achieved
Wednesday, January 24, 1996Foundation stone laid
Monday, February 26, 1996CEA (Central Electricity Authority) approval received
Saturday, August 30, 1997Initial commissioning date
Wednesday, October 22, 1997First unit commissioned
Tuesday, October 28, 1997CCFI (Cabinet Committee on Foreign Investment) approval received
Tuesday, June 30, 1998Third Unit Commissioned
Tuesday, June 30, 1998Second Unit Commissioned
Friday, December 25, 1998Completed

More projects (By Gujarat Paguthan Energy Corpn. Pvt. Ltd.):
• Paguthan Power• Belgaum Wind Farm• Samana Wind Power Project - Phase I
• Samana Wind Power Project - Phase Ii
Videos   |   Useful Links   |   FREE Magazines
HomeBuyAdd FREE ListingAdvertise Industrial CompanyIndustrial Portal