Project Status: Completed  Project Type/Scale: New Unit
Industry: Pig iron
Investment/Estimated Cost: Rs. 662.00 Crores / USD 165.50 Million
Thursday, September 8, 1994Public issue (Rs. 13.75 Crores)
Thursday, August 31, 1995Trial run expected
Tuesday, October 31, 1995Initial commissioning date
Thursday, November 30, 1995Expenses incurred till 1 (Rs. 255.00 Crores)
Wednesday, February 28, 1996Revised commissioning date
Tuesday, December 31, 1996Revised commissioning date
Tuesday, September 30, 1997Revised commissioning date
Thursday, December 31, 1998Revised commissioning date
Tuesday, September 28, 2004Stalled upto
Friday, December 31, 2004Revised commissioning date
Thursday, March 31, 2005Partially commissioned
Saturday, December 31, 2005Completed