Industrial Projects > Pig iron > Pig Iron Project
Pig Iron Project
Company: Mideast Integrated Steels Ltd.
Ownership: Mesco Group
Project Location: Khurunti, Dist. Cuttack, Orissa, India
Phone: 0674-2432759/2432755/2432256
Contact: Rita Singh / MD Secondary Contact: J.K. Singh / Chairman
Project Status: Completed Project Type/Scale: New Unit
Industry: Pig iron
Investment/Estimated Cost: Rs. 662.00 Crores / USD 165.50 Million
More projects (By Mideast Integrated Steels Ltd.):
Ownership: Mesco Group
Project Location: Khurunti, Dist. Cuttack, Orissa, India
Phone: 0674-2432759/2432755/2432256
Contact: Rita Singh / MD Secondary Contact: J.K. Singh / Chairman
Project Status: Completed Project Type/Scale: New Unit
Industry: Pig iron
Investment/Estimated Cost: Rs. 662.00 Crores / USD 165.50 Million
Thursday, September 8, 1994 | Public issue (Rs. 13.75 Crores) |
---|---|
Thursday, August 31, 1995 | Trial run expected |
Tuesday, October 31, 1995 | Initial commissioning date |
Thursday, November 30, 1995 | Expenses incurred till 1 (Rs. 255.00 Crores) |
Wednesday, February 28, 1996 | Revised commissioning date |
Tuesday, December 31, 1996 | Revised commissioning date |
Tuesday, September 30, 1997 | Revised commissioning date |
Thursday, December 31, 1998 | Revised commissioning date |
Tuesday, September 28, 2004 | Stalled upto |
Friday, December 31, 2004 | Revised commissioning date |
Thursday, March 31, 2005 | Partially commissioned |
Saturday, December 31, 2005 | Completed |
More projects (By Mideast Integrated Steels Ltd.):
• | Steel | • | Steel |