Industrial Projects > Electricity Generation > Pumped Storage Plant Project
Pumped Storage Plant Project
Company: Tata Power Co. Ltd.
Ownership: Tata Group
Project Location: Bhira, Distt. Raigad, Maharashtra, India
Contact: S Ganguly / Vice CH Secondary Contact: D G Mehra / Wholetime Director
Project Status: Completed Project Type/Scale: Substantial Expansion
Industry: Electricity Generation
Investment/Estimated Cost: Rs. 240.00 Crores / USD 60.00 Million
More projects (By Tata Power Co. Ltd.):
Ownership: Tata Group
Project Location: Bhira, Distt. Raigad, Maharashtra, India
Contact: S Ganguly / Vice CH Secondary Contact: D G Mehra / Wholetime Director
Project Status: Completed Project Type/Scale: Substantial Expansion
Industry: Electricity Generation
Investment/Estimated Cost: Rs. 240.00 Crores / USD 60.00 Million
Thursday, November 30, 1995 | Initial commissioning date |
---|---|
Saturday, November 30, 1996 | Revised commissioning date |
Friday, January 31, 1997 | Completion by |
Saturday, May 31, 1997 | Completed |