Industrial Projects > Electricity Distribution > Raipur-Chandrapur(Raipur-Palandur) Transmission Project
Raipur-Chandrapur(Raipur-Palandur) Transmission Project
Company: Power Grid Corpn. Of India Ltd.
Ownership: Central Govt. - Commercial Enterprises
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Distribution
Investment/Estimated Cost: Rs. 248.60 Crores / USD 62.15 Million
More projects (By Power Grid Corpn. Of India Ltd.):
Ownership: Central Govt. - Commercial Enterprises
Project Location: India
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Distribution
Investment/Estimated Cost: Rs. 248.60 Crores / USD 62.15 Million
Friday, June 28, 2002 | Project bids awarded |
---|---|
Monday, July 1, 2002 | Date of announcement |
Monday, January 31, 2005 | Expenses incurred till 1 (Rs. 212.43 Crores) |
Thursday, March 31, 2005 | Expenses incurred till 1 (Rs. 225.88 Crores) |
Thursday, March 31, 2005 | Revised commissioning date |
Saturday, December 31, 2005 | Completion by |
Friday, March 31, 2006 | Completed |