Industrial Projects > Railway Transport > Secunderabad-Dronachallam G C Project
Secunderabad-Dronachallam G C Project
Company: South Central Railways
Ownership: Central Govt. - Departmental Undertaking
Project Location: India
Project Status: Completed Project Type/Scale: Renovation - Moderate
Industry: Railway Transport
Investment/Estimated Cost: Rs. 341.88 Crores / USD 85.47 Million
More projects (By South Central Railways):
Ownership: Central Govt. - Departmental Undertaking
Project Location: India
Project Status: Completed Project Type/Scale: Renovation - Moderate
Industry: Railway Transport
Investment/Estimated Cost: Rs. 341.88 Crores / USD 85.47 Million
Thursday, April 30, 1992 | Central Government approval received |
---|---|
Sunday, June 30, 1996 | Initial commissioning date |
Monday, March 31, 1997 | Expenses incurred till 1 (Rs. 177.98 Crores) |
Tuesday, March 31, 1998 | Expenses incurred till 1 (Rs. 267.88 Crores) |
Wednesday, March 31, 1999 | Completed |
Wednesday, March 31, 1999 | Expenses incurred till 1 (Rs. 297.18 Crores) |
Friday, March 31, 2000 | Expenses incurred till 1 (Rs. 332.58 Crores) |
Saturday, March 31, 2001 | Budgetary allocation (Rs. 5.00 Crores) |