Industrial Projects > Finished steel > Steel Products Project
Steel Products Project
Company: Kamper Concast Ltd.
Ownership: Ambuja (Bihar) Group
Project Location: N.H. No.30,Bihta, Dist.Patna, Bihar, India
Contact: Pawan Gupta / Director Secondary Contact: Purushottam Kumar Gupta / Director
Project Status: Completed Project Type/Scale: New Unit
Industry: Finished steel
Investment/Estimated Cost: Rs. 10.94 Crores / USD 2.74 Million
Ownership: Ambuja (Bihar) Group
Project Location: N.H. No.30,Bihta, Dist.Patna, Bihar, India
Contact: Pawan Gupta / Director Secondary Contact: Purushottam Kumar Gupta / Director
Project Status: Completed Project Type/Scale: New Unit
Industry: Finished steel
Investment/Estimated Cost: Rs. 10.94 Crores / USD 2.74 Million
Thursday, June 22, 1995 | Expenses incurred till 1 (Rs. 0.95 Crores) |
---|---|
Tuesday, December 12, 1995 | Public issue (Rs. 10.07 Crores) |
Friday, May 31, 1996 | Trial run expected |
Friday, May 31, 1996 | Machinery installed |
Wednesday, July 31, 1996 | Initial commissioning date |
Tuesday, December 31, 1996 | Commercial production expected |
Friday, May 16, 1997 | Completed |