Industrial Projects > Road Transport > Tuni-Rajahmundry(Tuni-Dharmavaram) Highway Project
Tuni-Rajahmundry(Tuni-Dharmavaram) Highway Project
Company: Rajahmundry Expressway Ltd.
Ownership: Joint Sector
Project Location: India
Contact: L Chhabra / Director Secondary Contact: P K Umrigar / Director
Project Status: Active Project Type/Scale: Renovation - Moderate / Substantial Expansion
Industry: Road Transport
Investment/Estimated Cost: Rs. 300.00 Crores / USD 75.00 Million
Ownership: Joint Sector
Project Location: India
Contact: L Chhabra / Director Secondary Contact: P K Umrigar / Director
Project Status: Active Project Type/Scale: Renovation - Moderate / Substantial Expansion
Industry: Road Transport
Investment/Estimated Cost: Rs. 300.00 Crores / USD 75.00 Million
Monday, December 25, 2000 | Project bids awarded |
---|---|
Saturday, March 31, 2001 | Expenses incurred till 1 (Rs. 0.07 Crores) |
Saturday, June 30, 2001 | Project bids awarded |
Saturday, June 30, 2001 | Date on which environmental clearance was received |
Sunday, March 31, 2002 | Expenses incurred till 1 (Rs. 1.03 Crores) |
Monday, March 31, 2003 | Expenses incurred till 1 (Rs. 83.83 Crores) |
Wednesday, December 31, 2003 | Initial commissioning date |
Wednesday, March 31, 2004 | Expenses incurred till 1 (Rs. 181.10 Crores) |
Tuesday, November 30, 2004 | Revised commissioning date |