Industrial Projects > Electricity Generation - Thermal-Lignite Based > Zero Unit Power Project
Zero Unit Power Project
Company: S T-C M S Electric Co. Pvt. Ltd.
Ownership: Private (Foreign)
Project Location: Oxford Centre, 1st floor,66 C P Ramaswamy Rd., Alwarpet, Chennai, India Fax: 91-44-4987814
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Generation - Thermal-Lignite Based
Investment/Estimated Cost: Rs. 1,200.00 Crores / USD 300.00 Million
Ownership: Private (Foreign)
Project Location: Oxford Centre, 1st floor,66 C P Ramaswamy Rd., Alwarpet, Chennai, India Fax: 91-44-4987814
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Generation - Thermal-Lignite Based
Investment/Estimated Cost: Rs. 1,200.00 Crores / USD 300.00 Million
Saturday, August 8, 1992 | MoU signed |
---|---|
Monday, October 4, 1993 | PPA (Power purchase agreement) signed |
Friday, August 19, 1994 | CEA (Central Electricity Authority) approval received |
Saturday, April 1, 1995 | Date of announcement |
Thursday, March 7, 1996 | Central Government approval received |
Wednesday, November 20, 1996 | PPA (Power purchase agreement) signed |
Wednesday, December 31, 1997 | Initial commissioning date |
Friday, December 31, 1999 | Revised commissioning date |
Friday, December 31, 1999 | Financial closure achieved |
Monday, May 1, 2000 | Expenses incurred till 1 (Rs. 30.00 Crores) |
Friday, October 11, 2002 | Trial run commenced |
Monday, December 30, 2002 | Completion by |
Tuesday, December 31, 2002 | Completed |