Zero Unit Power Project

Company: S T-C M S Electric Co. Pvt. Ltd.
Ownership: Private (Foreign)
Project Location: Oxford Centre, 1st floor,66 C P Ramaswamy Rd., Alwarpet, Chennai, India   Fax: 91-44-4987814

Project Status: Completed  Project Type/Scale: New Unit
Industry: Electricity Generation - Thermal-Lignite Based
Investment/Estimated Cost: Rs. 1,200.00 Crores / USD 300.00 Million
Saturday, August 8, 1992MoU signed
Monday, October 4, 1993PPA (Power purchase agreement) signed
Friday, August 19, 1994CEA (Central Electricity Authority) approval received
Saturday, April 1, 1995Date of announcement
Thursday, March 7, 1996Central Government approval received
Wednesday, November 20, 1996PPA (Power purchase agreement) signed
Wednesday, December 31, 1997Initial commissioning date
Friday, December 31, 1999Revised commissioning date
Friday, December 31, 1999Financial closure achieved
Monday, May 1, 2000Expenses incurred till 1 (Rs. 30.00 Crores)
Friday, October 11, 2002Trial run commenced
Monday, December 30, 2002Completion by
Tuesday, December 31, 2002Completed