Company: Andhra Pradesh State Electricity Board
Ownership: State Electricity Boards
Project Location: Paloncha,Khamman Distt., Andhra Pradesh, India
Project Status: Completed Project Type/Scale: Substantial Expansion
Industry: Electricity Generation - Coal Based
Investment/Estimated Cost: Rs. 1,890.00 Crores / USD 472.50 Million
More projects (By Andhra Pradesh State Electricity Board):
Ownership: State Electricity Boards
Project Location: Paloncha,Khamman Distt., Andhra Pradesh, India
Project Status: Completed Project Type/Scale: Substantial Expansion
Industry: Electricity Generation - Coal Based
Investment/Estimated Cost: Rs. 1,890.00 Crores / USD 472.50 Million
Thursday, December 9, 1993 | CEA (Central Electricity Authority) approval received |
---|---|
Thursday, March 31, 1994 | Planning Commission approval received |
Friday, March 28, 1997 | First unit commissioned |
Tuesday, March 31, 1998 | Initial commissioning date |
Sunday, September 6, 1998 | Completed |
Sunday, September 6, 1998 | Second Unit Commissioned |