Industrial Projects > Electricity Generation - Hydel Based > Singur Hydel Power Project
Singur Hydel Power Project
Company: Andhra Pradesh State Electricity Board
Ownership: State Electricity Boards
Project Location: Singur, Medak, Andhra Pradesh, India
Contact: J Parthaasarathy / MD
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 40.58 Crores / USD 10.15 Million
More projects (By Andhra Pradesh State Electricity Board):
Ownership: State Electricity Boards
Project Location: Singur, Medak, Andhra Pradesh, India
Contact: J Parthaasarathy / MD
Project Status: Completed Project Type/Scale: New Unit
Industry: Electricity Generation - Hydel Based
Investment/Estimated Cost: Rs. 40.58 Crores / USD 10.15 Million
Tuesday, October 31, 1989 | CEA (Central Electricity Authority) approval received |
---|---|
Wednesday, March 31, 1993 | Expenses incurred till 1 (Rs. 4.33 Crores) |
Thursday, March 31, 1994 | Initial commissioning date |
Tuesday, March 31, 1998 | Revised commissioning date |
Tuesday, March 31, 1998 | Expenses incurred till 1 (Rs. 24.26 Crores) |
Wednesday, March 31, 1999 | Revised commissioning date |
Wednesday, December 15, 1999 | Partially commissioned |
Monday, January 31, 2000 | Completed |
Friday, March 31, 2000 | Revised commissioning date |