Find Projects:
 Industrial Projects > Electricity Generation > Mejia Phase Vii & Viii Thermal Power Project

Mejia Phase Vii & Viii Thermal Power Project

Company: Damodar Valley Corpn.
Ownership: Central Govt. - Statutory Bodies
Project Location: India

Project Status: Active  Project Type/Scale: New Unit
Industry: Electricity Generation
Investment/Estimated Cost: Rs. 4,546.60 Crores / USD 1,136.65 Million
Wednesday, September 13, 2006Date on which environmental clearance was sought
Saturday, December 9, 2006Board of Directors approval
Saturday, December 9, 2006Date of announcement
Tuesday, June 19, 2007Foundation stone laid
Sunday, September 30, 2007Completion by

More projects (By Damodar Valley Corpn.):
• Bokaro Dual Fuel Based Power• Bokaro Thermal Power Station R & M• Btps-Ramgarh Transmission Line
• Chandrapura Thermal Power Station R & M• Durgapur Power• Kodarma Power
• Maithon R & M• Mejia Phase Iv Power• Mejia Power
• Mejia Unit V & Vi Thermal Power• Mejia-Borjora Power Transmission Line• Panagarh Substation
• Panchet Thermal Power• Patherdih-Govindpur 132 Kv Transmission• Raghunathpur Power
• Ramgarh Power• Bolpur Iti• Chas Iti Upgradation
• Chhatna Iti Upgradation• Durgapur Iti Upgradation• Hazaribagh Iti Upgradation
• Koderma Iti• Purulia Iti Upgradation• Koderma Power Project Phase-Ii
Videos   |   Useful Links   |   FREE Magazines
HomeBuyAdd FREE ListingAdvertise Industrial CompanyIndustrial Portal