Company: Damodar Valley Corpn.
Ownership: Central Govt. - Statutory Bodies
Project Location: Bankura, Distt. Bankura, West Bengal, India
Contact: T.P. Mandal / Director  Secondary Contact: J. Vasudevan / Chairman

Project Status: Completed  Project Type/Scale: New Unit
Industry: Electricity Generation - Coal Based
Investment/Estimated Cost: Rs. 1,989.14 Crores / USD 497.29 Million
Thursday, March 20, 1986Planning Commission approval received
Wednesday, September 30, 1992Initial commissioning date
Sunday, March 31, 1996Expenses incurred till 1 (Rs. 1,231.61 Crores)
Tuesday, December 31, 1996Expenses incurred till 1 (Rs. 1,650.07 Crores)
Monday, March 31, 1997Budgetary allocation (Rs. 250.00 Crores)
Monday, March 31, 1997Revised commissioning date
Wednesday, December 31, 1997Revised commissioning date
Tuesday, March 31, 1998Expenses incurred till 1 (Rs. 1,889.86 Crores)
Wednesday, March 31, 1999Completed

More projects (By Damodar Valley Corpn.):
• Bokaro Dual Fuel Based Power• Bokaro Thermal Power Station R & M• Kodarma Power
• Mejia Phase Iv Power• Raghunathpur Power• Ramgarh Power
• Mejia Phase Vii & Viii Thermal Power• Chandrapura Thermal Power Station R & M• Durgapur Power
• Mejia Unit V & Vi Thermal Power• Panchet Thermal Power• Koderma Power Project Phase-Ii
• Maithon R & M• Btps-Ramgarh Transmission Line• Mejia-Borjora Power Transmission Line
• Panagarh Substation• Patherdih-Govindpur 132 Kv Transmission• Bolpur Iti
• Chas Iti Upgradation• Chhatna Iti Upgradation• Durgapur Iti Upgradation
• Hazaribagh Iti Upgradation• Koderma Iti• Purulia Iti Upgradation
Videos   |   Useful Links   |   FREE Magazines
HomeBuyAdd FREE ListingAdvertise Industrial CompanyIndustrial Portal