Industrial Projects > Finished steel > Bhilai Sinter Plant-3 Project
Bhilai Sinter Plant-3 Project
Company: Steel Authority Of India Ltd.
Ownership: Central Govt. - Commercial Enterprises
Project Location: Bhilai, Distt. Durg, Madhya Pradesh, India
Contact: C.S. Tiwari / Exec. Director - Works Secondary Contact: V. Gujaral / MD - Bhilai
Project Status: Completed Project Type/Scale: New Unit
Industry: Finished steel
Investment/Estimated Cost: Rs. 809.72 Crores / USD 202.43 Million
More projects (By Steel Authority Of India Ltd.):
Ownership: Central Govt. - Commercial Enterprises
Project Location: Bhilai, Distt. Durg, Madhya Pradesh, India
Contact: C.S. Tiwari / Exec. Director - Works Secondary Contact: V. Gujaral / MD - Bhilai
Project Status: Completed Project Type/Scale: New Unit
Industry: Finished steel
Investment/Estimated Cost: Rs. 809.72 Crores / USD 202.43 Million
Sunday, March 31, 1996 | Expenses incurred till 1 (Rs. 55.26 Crores) |
---|---|
Monday, March 31, 1997 | Expenses incurred till 1 (Rs. 114.04 Crores) |
Tuesday, March 31, 1998 | Initial commissioning date |
Tuesday, June 30, 1998 | Expenses incurred till 1 (Rs. 211.44 Crores) |
Wednesday, March 31, 1999 | Revised commissioning date |
Wednesday, June 30, 1999 | Expenses incurred till 1 (Rs. 614.68 Crores) |
Monday, July 31, 2000 | Revised commissioning date |
Saturday, March 31, 2001 | Revised commissioning date |
Monday, February 4, 2002 | Completed |
More projects (By Steel Authority Of India Ltd.):