Industrial Projects > Finished steel > Durgapur Bloom Caster Project
Durgapur Bloom Caster Project
Company: Steel Authority Of India Ltd.
Ownership: Central Government
Project Location: India
Contact: S K Bhattacharya / MD
Project Status: Active Project Type/Scale: Renovation - Moderate
Industry: Finished steel
Investment/Estimated Cost: Rs. 271.41 Crores / USD 67.85 Million
More projects (By Steel Authority Of India Ltd.):
Ownership: Central Government
Project Location: India
Contact: S K Bhattacharya / MD
Project Status: Active Project Type/Scale: Renovation - Moderate
Industry: Finished steel
Investment/Estimated Cost: Rs. 271.41 Crores / USD 67.85 Million
Wednesday, October 1, 2003 | Date of announcement |
---|---|
Thursday, March 31, 2005 | Expenses incurred till 1 (Rs. 11.90 Crores) |
Wednesday, August 31, 2005 | Initial commissioning date |
Saturday, December 31, 2005 | Expenses incurred till 1 (Rs. 72.63 Crores) |
Friday, March 31, 2006 | Expenses incurred till 1 (Rs. 101.30 Crores) |
Wednesday, May 31, 2006 | Revised commissioning date |
Friday, June 30, 2006 | Expenses incurred till 1 (Rs. 135.12 Crores) |
Tuesday, November 14, 2006 | Date on which environmental clearance was sought |
Thursday, March 29, 2007 | Date on which environmental clearance was received |
More projects (By Steel Authority Of India Ltd.):