Company: Steel Authority Of India Ltd.
Ownership: Central Govt. - Commercial Enterprises
Project Location: Bokaro Steel City, Distt. Giridih, Bihar, India
Contact: B. Ghoshal / Exec. Director - Works Secondary Contact: B.K. Singh / MD - Bokaro
Project Status: Completed Project Type/Scale: Renovation - Moderate / Substantial Expansion
Industry: Finished steel
Investment/Estimated Cost: Rs. 2,235.45 Crores / USD 558.86 Million
More projects (By Steel Authority Of India Ltd.):
Ownership: Central Govt. - Commercial Enterprises
Project Location: Bokaro Steel City, Distt. Giridih, Bihar, India
Contact: B. Ghoshal / Exec. Director - Works Secondary Contact: B.K. Singh / MD - Bokaro
Project Status: Completed Project Type/Scale: Renovation - Moderate / Substantial Expansion
Industry: Finished steel
Investment/Estimated Cost: Rs. 2,235.45 Crores / USD 558.86 Million
Monday, May 31, 1993 | PIB (Public Investment Board) approval received |
---|---|
Wednesday, July 7, 1993 | Cabinet approval received |
Thursday, March 31, 1994 | Expenses incurred till 1 (Rs. 9.50 Crores) |
Sunday, December 31, 1995 | Expenses incurred till 1 (Rs. 416.37 Crores) |
Saturday, November 30, 1996 | Initial commissioning date |
Monday, June 30, 1997 | Expenses incurred till 1 (Rs. 1,669.15 Crores) |
Saturday, February 28, 1998 | Revised commissioning date |
Tuesday, March 31, 1998 | Trial run commenced |
Tuesday, March 31, 1998 | Budgetary allocation (Rs. 590.00 Crores) |
Sunday, February 28, 1999 | Completed |